Harlow Council has hired architects Ackroyd Lowrie to design the regeneration of Market Square, with up to £300,000 approved. The council now owns three buildings there.

Harlow Council has appointed architects to design the next stage of work on Market Square. The Leader of the Council, Councillor Dan Swords, approved spending of up to £300,000 on the contract on Monday 10 November.

The firm is Ackroyd Lowrie Limited. It will be the architect and lead designer for the council’s “regeneration projects within Market Square”, according to the decision record, published on Wednesday.

Why the council is doing this

The council now owns three of the main buildings around the square. The signed report behind the decision names them:

  • Market House
  • Adams House, the building with the large clock
  • The Rows

Owning them means the council no longer has to rely “on separate owners to bring forward improvements”, the report says. Instead it can plan the buildings and the square together.

The stated aims are to bring “vacant and underused accommodation back into productive use” and to strengthen the town centre’s “leisure, hospitality and commercial offer”.

Some of that is already moving. In August the council agreed to lease the ground floor of Adams House. The decision said this would support “the transformation of the northern end of the town centre into a vibrant destination for residents and visitors to enjoy leisure, hospitality, and nightlife”.

How the deal works

  • Who: Ackroyd Lowrie Limited, chosen as the “preferred provider” after a procurement through the NEPRO Innovation framework, run by Constellia Public Limited. The council’s contract is with Constellia.
  • How much: up to £300,000 from the existing Non-Housing Capital Programme. That covers the current work, Constellia’s management fee and any extra design work.
  • What is secret: the statement of work and the fee breakdown are in an appendix kept confidential for commercial reasons.
  • Who decides the detail: the council’s Executive Director for Communities and Regeneration, with the Leader, can agree the scope and add work within the £300,000.

The report says the council chose one appointment rather than a separate tender for each building. It says separate tenders “would increase procurement timescales and reduce continuity across the project”.

The decision was not open to call-in by other councillors.

What it means for you

The report does not say what will be built, what the buildings will be used for, or when work will start. Those details depend on the designs this contract pays for.

Changes to the outside of the buildings or to the square itself would normally need planning permission. That would mean a public consultation on the Harlow planning register. We will report the plans when they are published.